Akosombo and Kpong Dams

NORPLAN AS on behalf of Multiconsult AS entered a Joint Venture with Royal Haskonig (NL ) to undertake a DS A and EPP for the existing dams and appurtenant structures.

The Dams are rockfill dams (max. height at Akosombo 141m, Kpong 19 m, fill volume 7.9 Mm3 (Akosombo) and 1.4 Mm3 (Kpong). Included are power station (Kpong), intake and penstocks (Akosombo), and spillways (12 radial gates and Akosombo and 15 radial gates at Kpong).

Inundation maps were prepared based on LiDAR mapping. Inundated area covers about 1,500 km2. An extensive GIS based database of the potentially affected area was prepared showing location of villages, local institutions and safe havens. EPP ’s include institutional and legal requirements as well as emergency action plans

Scope of work

Mobilization, inspections, data collection and assessment of structures mechanical and civil. New flood estimates (by JV partner) and preparation of routing procedures for the gated dams. Establishment of earthquake loads and stability analyses. Suggestions for improvements to meet current international good practice standards for the DSA (Dam Safety Assessment). Aerial mapping (LiDAR) of downstream areas affected by a potential dambreak and preparation of inundation maps. Identification of local government structures, villages, safe havens. Preparation of communication directory and emergency action plans for the EPP (Emergency Preparedness Plan). Training and workshops for both parts of the assignment.

Engineering services

Condition assessment (structural, civil, mechanical and monitoring)
Design review – new loads
Hydropower Generation Assessment
Assessment of ASR